1
|
Bank XXX Indonesia
|
PT. Aba
Sarana Lestari
|
Backbone
& LAN Infrastructure Installation, Bank XXX (*), Tower II.
* On-going Project/Classified
|
- Fiber Optic Backbone
Installation
- Data Center Horizontal Cabling = 800 nodes
- Horizontal Cabling for User Access = 2400 nodes
|
2007
|
|
|
|
|
|
|
|
|
2
|
Ericsson Indonesia
|
PT. SBI
|
Backbone,
LAN and Voice recabling, Ericsson Indonesia Building.
|
- Fiber Optic Backbone
Installation
- Data Center Horizontal Cabling = 240 nodes
- Horizontal Cabling for User Access = 260 nodes
- Voice Cabling = 1435 nodes
- Voice IDF Installation
|
2007
|
|
|
|
|
|
|
|
|
3
|
PT. Takeda
Indonesia
|
PT. Takeda
Indonesia
|
LAN &
Voice recabling
|
-
Horizontal Cabling for User Access = 26 node
- Voice Cabling = 35 node
- Voice IDF Installation
|
2007
|
|
|
|
|
|
|
|
|
4
|
AJB
Bumiputera 1912
|
AJB
Bumiputera 1912
|
Backbone
& LAN Infrastructure Installation at Wisma AJB Bumiputera 1912.
Data Center /Servers Relocation
|
-
Horizontal Cabling for User Access = 208 nodes
- Racks / Server Relocation
- Active Devices
|
2007
|
|
|
|
|
|
|
|
|
5
|
Bank XXX Indonesia
|
PT. Aba
Sarana Lestari
|
Backbone
& LAN Infrastructure Installation, Bank XXX (*), Tower I.
* On-going Project/Classified
|
- Fiber Optic Backbone
Installation
- Data Center Horizontal Cabling = 730 nodes
- Horizontal Cabling for User Access = 1400 nodes
|
2007
|
|
|
|
|
|
|
|
|
6
|
Bank BRI
Pusat
|
PT.
Swadharma Duta Data
|
PMS-LAN Infrastructure and BRI-net setup.
( BRI Unit Offices, regional: Jawa Barat, Jawa Timur, Kalimantan Timur etc. sum=73
location )
|
- LAN,
Electrical and Grounding
- PC to BRI-Net setup
|
2006
|
|
|
|
|
|
|
|
|
7
|
PLN
Wilayah NTT
|
PT.
Central Energi Pratama
|
SCADA
Development for PLN Cabang Kupang
|
Data &
Voice Infrastructure:
- Fiber Optic
- Radio Communication
- Voice Over IP
- Horizontal Cabling
|
2006
|
|
|
|
|
|
|
|
|
8
|
PLN Kantor Sektor Kit Bukittinggi
|
PLN Kantor Sektor Kit Bukittinggi
|
Server
Room Development and LAN reconfiguration
|
- Racks, UPS & Active Devices
- Horizontal Cabling
- Wireless Network
|
2006
|
|
|
|
|
|
|
|
|
9
|
BNI Kantor
Cab. Samarinda
|
PT.
Swadharma Duta Data
|
LAN Installation BNI cabang Samarinda
|
-
Horizontal Cabling
- LAN & WAN Configuration
|
2006
|
|
|
|
|
|
|
|
|
10
|
PT. Sansyu
Precision Indonesia
|
PT. Sansyu
Precision Indonesia
|
Servers
and Horizontal Cabling
|
- Servers
Supply, including setup and installation
- Active Devices and Firewall
- Horizontal Cabling
|
2006
|
|
|
|
|
|
|
|
|
11
|
Total
Indonesie East Kalimantan
|
Transmetco
|
Fiber
optic installation at Total Indonesie
|
Fiber Otic
Supply & Installation
|
2006
|
|
|
|
|
|
|
|
|
12
|
PT. Air Mancur
|
PT. Air Mancur
|
Computer
Hardware & Network Maintenance
|
-
Maintenance Local Area Network 97 node
- Maintenance PC and Printer
- Maintenance Switchcing and Router
- Maintenance Server
|
2006 -
2007
|
|
|
|
|
|
|
|
|
13
|
PT. Bank BNI , Kantor Besar
|
PT.
Swadharma Duta Data
|
Outsourcing Maintenance Infrastruktur di Kantor Besar
BNI Jakarta
|
-
Maintenance Local Area Network 4000 node
- Maintenance Fiber Optic Backbone
- Maintenance Grounding
- Maintenance Horizontal Cable at Data Center
- Maintenance Horizontal Cable at DRC
|
2006 -
2007
|
|
|
|
|
|
|
|
|
14
|
PT.
Swadharma Sarana Informatika
|
PT.
Swadharma Sarana Informatika
|
Horizontal
Cabling
|
Horizontal
Cabling
|
2006
|
|
|
|
|
|
|
|
|
15
|
PT.
Pertamina DOH JBB
|
PT.
Pertamina DOH JBB
|
Automation
System Repairment - Data Accuisition - Sub Master Cilamaya
|
- Router
- Microwave Radio Setup and Configuration
- WAN setup and configuration
|
2005
|
|
|
|
|
|
|
|
|
16
|
PLN Sektor
Kit Bukittinggi
|
PLN Sektor
Kit Bukittinggi
|
Campus and
Local Area Network Upgrade, PT. PLN Sektor Pembangkitan Bukittinggi
|
- Wireless
LAN
- Active Devices
|
2005
|
|
|
|
|
|
|
|
|
17
|
PLN Unit
Pembangkitan Singkarak
|
PT. Buana
Reksa
|
Fiber
Optic for HEPP (PLTA) Control System
|
- Fiber
Optic Supply & Installation
|
2005
|
|
|
|
|
|
|
|
|
18
|
US Namru
|
US Namru
|
Lan Cable
Installation for Opennet : US Namru Jakarta
|
Horizontal
Cabling
|
2005
|
|
|
|
|
|
|
|
|
19
|
Karstadt
Quelle Indonesia
|
Karstadt
Quelle Indonesia
|
Local Area
Network Installation at Karstadt Quelle Indonesia
|
-
Horizontal Cabling
- WAN Configuration
|
2005
|
|
|
|
|
|
|
|
|
20
|
PT. Bank BNI, Kantor Besar
|
PT. Swadharma Duta Data
|
Maintenance
Services for LAN Infrastructure, PC Terminal & LAN Peripherals at Kantor
Besar & DRC BNI
|
-
Maintenance PC dan Printer
- Maintenance Local Area Network 4000 node
- Maintenance Fiber Optic Backbone
- Maintenance Grounding
- Maintenance Horizontal Cable at Data Center
- Maintenance Horizontal Cable at DRC
|
2005 -
2006
|
|
|
|
|
|
|
|
|
21
|
Siemens Indonesia
|
Siemens Indonesia
|
Fiber
optic installation
|
Fiber
optic supply & installation
|
2005
|
|
|
|
|
|
|
|
|
22
|
Total
Indonesie, East Kalimantan
|
Siemens Indonesia
|
Fiber
optic installation
|
Fiber
optic supply & installation
|
2005
|
|
|
|
|
|
|
|